Force Majeure Clause Fails to Protect Oil and Gas Lessee From Mistakenly-Scheduled Deadline
The Energy Law Blog
MAY 5, 2023
2023), the Texas Supreme Court held that the lessee could not invoke a force majeure clause to save its oil and gas leases when it inadvertently scheduled its operations to begin after the requisite deadline. MRC did not notice its error until approximately two weeks after May 21, 2017, at which point it had not yet spudded the new well.