Force Majeure Clause Fails to Protect Oil and Gas Lessee From Mistakenly-Scheduled Deadline

The Energy Law

The leases obligated MRC to spud a new well every 180 days after the spud date of the last well during the leases’ secondary terms to avoid having the non-developed portions of the leases terminate. MRC did not notice its error until approximately two weeks after May 21, 2017, at which point it had not yet spudded the new well.

Spud-in 98
article thumbnail

FIFTH CIRCUIT BEGINS TO CLEAN UP ITS JURISPRUDENCE ON HOW TO DETERMINE WHETHER A CONTRACT IS (OR IS NOT) MARITIME

The Energy Law

and (2) Does the contract provide or do the parties expect that a vessel will play a substantial role in the completion of the contract? Turning to the second test, the court noted that the specific work order for the P&A job called for the use of three vessels — a supply barge, a tug, and the spud barge OB 808.

E&P 40
article thumbnail

Louisiana Second Circuit Provides Guidance as to Good Faith Required When Conducting Operations Necessary to Interrupt Prescription of Mineral Servitude

The Energy Law

A well was spud on March 28, 2006. He pointed to owners having a cement truck waiting to fill the well as soon as drilling was completed as objective evidence of such an intent. During this downturn in activity, mineral rights owners must remain cognizant of the maintenance activities necessary to preserve their mineral rights.