Louisiana Third Circuit Affirms that LDNR Can Only Recover Emergency Response Costs Under La. R.S. 30:93(A)(4) from the Operator of Record and its Working Interest Owners
The Energy Law Blog
APRIL 12, 2022
The Lyon Well was leaking in 2018, which prompted the LDNR to task the current operator (Sandhill Production, Inc.) Sandhill never managed to stop the leak, and it abandoned the well in August 2019. 30:80 et seq. This revision to the OSRL also allowed the LDNR to tap into the Fund to pay for emergency response costs. Lyon Well #1.