Force Majeure Clause Fails to Protect Oil and Gas Lessee From Mistakenly-Scheduled Deadline
The Energy Law
MAY 5, 2023
In Point Energy Partners Permian, LLC v. In compliance with that obligation, MRC created a drilling schedule listing June 2, 2017 as the spud date of a new well based on its belief that the deadline to spud that well was June 19, 2017. The actual deadline, however, was May 21, 2017. MRC Permian Company , — S.W.3d